Aayush Buildwell Pvt. Ltd. Vs. Haryana Urban Development Authority
Housing – Allotment of Plot
Civil Appeal Nos. 2833-2834 of 2014 (Arising out of Special Leave Petition (Civil) Nos. 672- 673 of 2011)-Decided on 25-2-2014.
whether on the basis of a comparative analysis, the appellant was eligible to have allotment of a plot in its favour, and further while setting aside the process for allotment of plots, can it direct the process afresh allowing the ineligible candidates/parties to participate in the said fresh process….. we hold that the right of the appellant has not been crystallised. No right can be conferred on the appellant, granting allotment as has been prayed before us. In our opinion, the appellant has to comply with the process followed by HUDA to allot plots in favour of the allottees and, accordingly, we direct that if the appellant fulfils all the criteria laid down by HUDA in the process of allotment, HUDA shall consider its case for such allotment. In these facts and circumstances we direct that steps be taken by the appellant in accordance with the process of HUDA and if the criteria is being fulfilled by the appellant, HUDA shall take necessary steps in the matter for allotment in accordance with the provisions of law...read more